Start | End | Activity |
| 09/2005 | 04/2007 | Design |
| 03/2007 | 12/2007 | Site Preparation - Excavation and Foundations |
| 01/2008 | 02/2008 | Construction - Mobilization for Steel |
| 02/2008 | 10/2008 | Construction - Structural Steel Erection |
| 10/2008 | 10/2009 | Construction - Concrete, MEP Rough In |
| 03/2009 | 10/2009 | Construction - Curtain Wall / Exterior Facade |
| 09/2009 | 08/2010 | Construction - Fit Out / Interiors |
| 02/2010 | 09/2010 | Move-In / Commissioning / Turnover |