Week of April 16, 2007 –
· Test Chopping – Monday April 16th – 7:00 a.m. – noon.
· Earth removal continues throughout project site. Noise and dust conditions anticipated.
· Concrete wall removal will commence.· Opening in Driveway at 119th.
· Hard excavation work will commence under driveway.Week of April 23, 2007 –
· Earth removal continues throughout project site. Noise and dust conditions anticipated.
· Concrete wall removal continues.
· Hand excavation work under driveway (119th & Broadway)
· Site Fence Construction Revision:
· Broadway – Jersey barriers added*· Broadway – 2 Metered Parking Spaces to be taken off line*
· Broadway – Portion of Sidewalk will be closed*
· Broadway – Bus Stop Relocated to NE corner (M104, M4, M60)*
* Pending NYC Department of Transportation direction