Columbia University in the City of New York

04/16/2007 : April 16 and April 23, 2007

Construction Notification

 

Columbia University Morningside Campus

Northwest Science Project

(3030 Broadway)

Two Week Look Ahead

Week of April 16, 2007 –

 

·        Test Chopping – Monday April 16th – 7:00 a.m. – noon.

·        Earth removal continues throughout project site.  Noise and dust conditions anticipated.

·        Concrete wall removal will commence.

·        Opening in Driveway at 119th.

·        Hard excavation work will commence under driveway.

Week of April 23, 2007 –

·       Earth removal continues throughout project site.  Noise and dust conditions anticipated.

·    Concrete wall removal continues.

·        Hand excavation work under driveway (119th & Broadway)

·        Site Fence Construction Revision:

·        Broadway – Jersey barriers added*

·        Broadway – 2 Metered Parking Spaces to be taken off line*

·        Broadway – Portion of Sidewalk will be closed*

·        Broadway – Bus Stop Relocated to NE corner (M104, M4, M60)*

* Pending NYC Department of Transportation direction

Northwest Science Building up-dates can be found on the Neighbors Website (http://www.neighbors.columbia.edu/) under construction projects.

All inquiries, concerns and complaints should be addressed to projx@columbia.edu.  You can also contact Construction Coordination via the Facilities Call Center at:  (212) 854-2222.