For questions about a construction project, please contact the Columbia University Construction Helpline at projx@columbia.edu or the Columbia University Facilities Service Center at (212) 854-2222. And as a service to those interested in employment with construction firms currently working at Columbia , we have developed an Online referral process. | ![]() Construction Projects > Northwest Corner Building > Announcement Archive > Two Week Look Ahead 10/29/2007 : Two Week Look AheadConstruction Notification
Columbia University Morningside CampusNorthwest Science Project(3030 Broadway)
Two Week Look Ahead DODGE FITNESS CENTER IS OPEN FOR BUSINESS THROUGHOUT ENTIRE CONSTRUCTION PROJECT AND IS UNAFFECTED BY CONSTRUCTION ACTIVITY
Week of October 29th, 2007 –
· Intermittent rock chopping at foundations. Some noise and dust · Concrete Pour at footings and foundations. Some noise and dust · Cutting probes in select locations of Chandler and Pupin
· Demolition and removal of western façade of Dodge · Dodge roof /tennis court abatement
Week of November 5th, 2007 –
· Intermittent Rock Chopping at foundations · Soil removal · Relocation of Siamese connection at Dodge 119th & Broadway
· Relocation of sewer line @ 119th & Broadway Gate · Dodge roof /tennis court abatement. Abatement at night (9:00 p.m. – 5:30 a.m.) / Roofing (7 a.m. – 4 p.m.)
NOTE: · DOT has relocated the M60 bus stop from 120th & Broadway to 119th & Broadway. · DOT has re-located the M104 and M4 bus stop from the south corner of 120 & Bway to the northeast corner of 120th & Broadway Northwest Science Building up-dates can be found on the Neighbors Website (www.neighbors.columbia.edu) under construction projects.