For questions about a construction project, please contact the Columbia University Construction Helpline at projx@columbia.edu or the Columbia University Facilities Service Center at (212) 854-2222. And as a service to those interested in employment with construction firms currently working at Columbia , we have developed an Online referral process. | ![]() Construction Projects > Northwest Corner Building > Announcement Archive > Two Week Look Ahead - February 4, 2008 02/04/2008 : Two Week Look Ahead - February 4, 2008Construction Notification
Columbia University Morningside Campus McVickar Hall Project (622 West 113th Street)
Two Week Look Ahead
Week of February 4, 2008
· Continue masonry and carpentry work at roof, North, and West elevations. · Continue demolition work inside.
Week of February 11, 2007
· Continue masonry and carpentry work at roof, North, and West elevations. · Continue demolition work inside. · Install rigging at South elevation.
McVickar Hall project up-dates can be found on the Neighbors Website (www.neighbors.columbia.edu) under current construction projects. All inquiries and concerns should be addressed to projx@columbia.edu. We apologize for any inconvenience and appreciate your cooperation. Thank you.
|