Two Week Look Ahead
07/30/2007
:
Two Week Look Ahead
Construction Notification
Columbia University Morningside Campus
Northwest Science Project (3030 Broadway)
Two Week Look Ahead
DODGE FITNESS CENTER IS OPEN FOR BUSINESS THROUGHOUT ENTIRE CONSTRUCTION PROJECT AND IS UNAFFECTED BY CONSTRUCTION ACTIVITY
Week of July 30th, 2007 –
· Rock Chopping - *expected to continue until 6:00 p.m. each evening. Noise and slight dust conditions anticipated.
· Concrete set-up work under driveway (119th & Bway) – noise and minimal traffic impact anticipated.
Week of August 6th, 2007 –
· Rock Chopping - *expected to continue until 6:00 p.m. each evening – noise and some dust anticipated.
· Concrete set-up work under driveway (119th & Bway)
NOTE:
· DOT has relocated the M60 bus stop from 120th & Broadway to 119th & Broadway.
· DOT has re-located the M104 and M4 bus stop from the south corner of 120 & Bway to the northeast corner of 120th & Broadway
Northwest Science Building up-dates can be found on the Neighbors Website (www.neighbors.columbia.edu) under construction projects.
All inquiries, concerns and complaints should be addressed to projx@columbia.edu. You can also contact Construction Coordination via the Facilities Call Center at: (212) 854-2222.