Two Week Look Ahead - September 1, 2008
09/01/2008
:
Two Week Look Ahead - September 1, 2008
|
www.neighbors.columbia.edu
|
Construction Notification
Columbia University
Interdisciplinary Science Building
(3030 Broadway)
Two Week Look Ahead
DODGE FITNESS CENTER IS OPEN FOR BUSINESS THROUGHOUT ENTIRE CONSTRUCTION PROJECT AND IS UNAFFECTED BY CONSTRUCTION ACTIVITY. Levien Gymnasium has been re-opened.
saturday work permits have been requested for the next five weeks.
Week of September 1st, 2008–
· Steel Erection – Deck and welding
· Concrete placement at upper floor decks
· Campus Utilities – Utility work between CEPSR, Pupin, Dodge, and the North Service Tunnel
Week of September 8th, 2008 –
· Steel Erection – Deck and welding
· Concrete placement at upper floor decks
· Campus Utilities – Utilities work between CEPSR, Pupin, Dodge, and the North Service Tunnel
· Mobilize spray-on fireproofing operation
NOTE:
· DOT has relocated the M60 bus stop from West 120th & Broadway to West 119th Street & Broadway.
· DOT has re-located the M104 and M4 bus stop from the south corner of West 120th Street & Broadway to the northeast corner of West 120th Street & Broadway
Interdisciplinary Science Building up-dates can be found on the Neighbors Website (www.neighbors.columbia.edu) under construction projects. All inquiries, concerns and complaints should be addressed to projx@columbia.edu. You can also contact Construction Coordination via the Facilities Call Center at: (212) 854-2222.