03/03/2008 : Two Week Look Ahead

Construction Notification

 

Columbia University

Interdisciplinary Science Building

 

 

Two Week Look Ahead

DODGE FITNESS CENTER IS OPEN FOR BUSINESS THROUGHOUT ENTIRE CONSTRUCTION PROJECT AND IS UNAFFECTED BY CONSTRUCTION ACTIVITY

 

 

Week of March 3rd, 2008 –

 

 

·         Temporary crane in place through mid-March to set major columns & building tower - Noise and pedestrian and auto traffic restrictions. Lane reduction to two lanes on northbound Broadway.  Will re-open to three northbound lanes upon removal of temporary crane in mid-March.

 

·         Steel Erection – Trusses and building steel

 

·         Rock Chopping in NW corner of site, intermittent work. Noise and some dust conditions.

 

·         Guardrails to roof of Chandler building.

 

 

 

Week of March 10th, 2008 –

 

 

·         Temporary crane in place through mid-March to set major columns & building tower - Noise and pedestrian and auto traffic restrictions.

 

·         Steel Erection – Trusses and building steel

 

·         Rock Chopping in NW corner of site, intermittent work. Noise and some dust conditions.

 

·         Continue erection of sidewalk shed @ B’way & 120th street.

 

·         Start demolition at Chandler roof.

 

 

NOTE:

 

·          DOT has relocated the M60 bus stop from 120th & Broadway to 119th & Broadway.

 

·          DOT has re-located the M104 and M4 bus stop from the south corner of 120 & Bway to the northeast corner of 120th & Broadway

 

 