For questions about a construction project, please contact the Columbia University Construction Helpline at projx@columbia.edu or the Columbia University Facilities Service Center at (212) 854-2222. And as a service to those interested in employment with construction firms currently working at Columbia , we have developed an Online referral process. | ![]() Construction Projects > Northwest Corner Building > Announcement Archive > Two Week Look Ahead - July 7, 2008 07/07/2008 : Two Week Look Ahead - July 7, 2008Construction Notification
Columbia
University
Interdisciplinary
Science
Building
(3030 Broadway)
Two Week Look Ahead
GENERAL NOT:
DODGE
FITNESS
CENTER
’s FACILITIES REMAIN OPEN AND OPERATING THROUGHOUT OUR CONSTRUCTION. However, Levien Gymnasium (basketball courts) will be closed due to overhead construction until September 1, 2008.
Tower Crane has final DOB sign-off. Saturday work permits have been requested through August 4, 2008
Week of July 7th, 2008 –
· Steel Erection – Trusses and building steel at
North
Tower
– Some pedestrian and traffic disruption
· Welding work at trusses – Some noise
· Concrete placement at sub-cellar and upper floor decks – some noise
· Campus Utilities Work in CEPSR, Pupin, Dodge and the North Service Tunnel – Some noise and dust.
Week of July 14th, 2008 –
· Steel Erection – Trusses and building steel at north tower - Some traffic
· Sliding of trusses into final position – some noise
· Concrete placement – some noise
· Campus Utilities Work in CEPSR, Pupin, Dodge and the North Service Tunnel – Some noise and dust.
Interdisciplinary Science Building up-dates can be found on the Neighbors Web site (www.neighbors.columbia.edu) under construction projects.
All inquiries and concerns should be addressed to projx@columbia.edu. You can also contact Construction Coordination via the Facilities Call Center at: (212) 854-2222.
|