09/21/2009 : Two Week Look Ahead - September 21, 2009

Project Activities Two Week Look Ahead

Weeks of September 21, 2009 and September 28, 2009

Week of September 21, 2009

  • Delivery and installation of curtain wall panels
  • Mechanical, Electrical and Plumbing Rough-in work
  • Fireproofing (Intumescent Painting) on 600 Level

Week of September 28, 2009

  • Delivery and installation of curtain wall panels
  • Mechanical, Electrical and Plumbing Rough-in work

General Notes

  • Work hours are between 7:00 am and 3:00 pm unless otherwise noted.
  • Dodge Fitness Center is open for business throughout the entire construction project and is unaffected by construction activity. Levien Gymnasium has re-opened.
  • NYC DOT has relocated the M60 bus stop from West 120th & Broadway to West 119th Street & Broadway.
  • NYC DOT has re-located the M104 and M4 bus stop from the south corner of West 120th Street & Broadway to the northeast corner of West 120th Street & Broadway.