10/05/2009 : Two Week Look Ahead - October 5, 2009

Project Activities Two Week Look Ahead

Weeks of October 5, 2009 and October 12, 2009

Week of October 5, 2009

  • Delivery and installation of curtain wall panels
  • Mechanical, electrical and plumbing rough-in work
  • Fireproofing (intumescent painting) on 600 Level

Week of October 12, 2009

  • Delivery and installation of curtain wall panels continues
  • Mechanical, electrical and plumbing rough-in work continues

General Notes

  • Work hours are between 7:00 a.m. and 3:00 p.m., unless otherwise noted.
  • Dodge Fitness Center is open for business throughout the entire construction project and is unaffected by construction activity. Levien Gymnasium has re-opened.
  • NYC DOT has relocated the M60 bus stop from West 120th & Broadway to West 119th Street & Broadway.
  • NYC DOT has re-located the M104 and M4 bus stop from the south corner of West 120th Street & Broadway to the northeast corner of West 120th Street & Broadway.