Construction Projects
> Northwest Corner Building
> Announcement Archive >
Two Week Look Ahead - December 29, 2008
12/29/2008
:
Two Week Look Ahead - December 29, 2008
|
www.neighbors.columbia.edu
|
Construction Notification
Columbia University
Interdisciplinary Science Building
(3030 Broadway)
Two Week Look Ahead
DODGE FITNESS CENTER IS OPEN FOR BUSINESS THROUGHOUT ENTIRE CONSTRUCTION PROJECT AND IS UNAFFECTED BY CONSTRUCTION ACTIVITY. Levien Gymnasium has been re-opened.
saturday work permits have been requested for the next five weeks.
Week of December 29th, 2008 –
· Steel Erection – Deck and welding
· Campus Utilities – Utility work between CEPSR, Pupin, Dodge, and the North Service Tunnel
· Mobilize spray-on fireproofing operation
· Mechanical and plumbing work in cellar, and sub-cellar of new building
Week of January 5th, 2009 –
· Steel Erection – Deck and welding
· Concrete placement at upper floor decks
· Campus Utilities – Utilities work between CEPSR, Pupin, Dodge, and the North Service Tunnel
· Mobilize spray-on fireproofing operation
· Mechanical and plumbing work in cellar, and sub-cellar of new building
NOTE:
· DOT has relocated the M60 bus stop from West 120th & Broadway to West 119th Street & Broadway.
· DOT has re-located the M104 and M4 bus stop from the south corner of West 120th Street & Broadway to the northeast corner of West 120th Street & Broadway
Interdisciplinary Science Building up-dates can be found on the Neighbors Website (www.neighbors.columbia.edu) under construction projects. All inquiries, concerns and complaints should be addressed to projx@columbia.edu. You can also contact Construction Coordination via the Facilities Call Center at: (212) 854-2222.